Which of the following best describes planned outages?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

Planned outages refer to maintenance or upgrades scheduled beforehand to allow for necessary work on equipment or systems in the electrical grid. This advance scheduling is vital for coordination with grid operations, ensuring that the reliability and efficiency of the power supply are maintained. By planning these outages, operators can mitigate the impact on consumers and the overall electrical system, making it easier to manage generation and load while ensuring that necessary maintenance is completed without unexpected interruptions.

The other choices describe aspects that may be associated with outages but do not capture the most critical element—scheduling. Unscheduled maintenance happens unexpectedly and can create complications, while outages occurring only during off-peak hours might be a best practice, they are not a requirement for all planned outages. Additionally, while certain planned outages can be critical for system reliability, not all planned outages are strictly mandatory; they may be routine maintenance that enhances reliability but does not necessarily take precedence as critical without them. Therefore, the essence of planned outages lies in their scheduled nature, making advance planning the defining characteristic.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy