What is the deadline for submitting an outage request that is more than 5 days away?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

The correct answer indicates that an outage request that is more than 5 days away must be submitted 6 months in advance. This requirement is essential for managing the electrical grid effectively, as it allows sufficient time for planning and coordinating the necessary resources to accommodate the outage.

Advanced notice is crucial in transmission planning because outages can have significant impacts on system reliability and availability. By requiring a 6-month notice, PJM ensures that any necessary assessments, stakeholder engagement, and potential modifications to operations can occur well ahead of time, allowing for a more stable and secure grid environment.

The other options do not provide enough lead time for an outage of this nature, making them unsuitable for ensuring adequate preparation and compliance with operational protocols.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy