Outages scheduled for the following planning year that exceed how many days must be submitted via e-DART?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

Outages scheduled for the following planning year that exceed 30 days must be submitted via e-DART. This requirement ensures that long-term outages are effectively managed and coordinated within the PJM system. Submitting these outages through e-DART allows for better visibility and planning among stakeholders, helping to minimize the impact on system reliability and efficiency. This system facilitates communication and data tracking, which is especially crucial for outages that last longer, as they can significantly affect generation and transmission operations across the PJM region. By regulating the submission of extensive outages, PJM can maintain a stable and reliable electricity network while adequately preparing for any necessary maintenance or upgrades in advance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy