How much advance notice is needed for an ICCP Data Link outage request?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

In the context of an ICCP (Inter-Control Center Communications Protocol) Data Link outage request, the standard procedure requires a 24 business hours advance notice. This timeframe allows sufficient time for the coordination among various stakeholders involved in the transmission system to mitigate the impact of the outage.

The 24-hour notice is crucial since it enables personnel to adjust schedules, manage potential operational impacts, and communicate with affected parties about the outage. Such proactive measures ensure the stability and reliability of the transmission network during planned maintenance or unexpected outages.

Understanding the necessary notice period for maintenance requests, such as for ICCP Data Links, is essential for effective operation within the transmission system. This knowledge helps maintain compliance with operational protocols and fosters better communication between different control centers.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy