How many business days in advance must eDart tickets be submitted?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

eDart tickets must be submitted three business days in advance to ensure that all necessary processes can be efficiently executed. This advance notice allows the appropriate stakeholders to review and address any potential concerns regarding the proposed work or outages. It facilitates proper planning and coordination within the transmission system to minimize disruptions and ensure compliance with operational protocols. The three-day requirement provides ample time for necessary evaluations, stakeholder discussions, and adjustments, ensuring that all relevant parties are informed and can prepare accordingly. This practice supports the overall reliability and effectiveness of the transmission system operations.