For a transmission outage request submitted under the one month rule, when must it be provided?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

For a transmission outage request submitted under the one-month rule, it is important to adhere to the timeline requirements set by transmission organizations to ensure efficient operation and coordination among various entities. The correct timeframe for submitting this type of request is five days before the scheduled outage.

This timeline allows for adequate processing and coordination among operators, which helps to minimize disruptions and ensure that all parties are informed and prepared for the outage. A five-day advance notice strikes a balance between giving enough lead time for necessary preparations while still remaining relatively close to the actual outage date. This is essential for maintaining reliability in the transmission network and allows for necessary adjustments or accommodations in operations or maintenance activities.

Understanding this timing is crucial for effective planning and helps avoid issues that could arise from last-minute requests, which may lead to scheduling conflicts or operational inefficiencies.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy