For a 5-day outage starting in June, by when must the notice be submitted to be considered on time?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

To determine when the notice must be submitted for a 5-day outage in June to be considered on time, it's essential to understand the notice period typically required prior to such outages. In the context of PJM Transmission, notifications must be submitted well in advance to ensure that all necessary stakeholders can prepare and make adjustments as needed.

For a 5-day outage occurring in June, the notice period usually requires submission at least 30 days prior to the start of the outage. This means if the outage begins on a day in June, the latest acceptable date to submit the notification would be the last day of April.

Since April has only 30 days, the last day for submission is indeed April 30th. Notably, April 31st does not exist, making it an invalid option. Thus, the requirement is for notice to be submitted by April 30th, thereby ensuring compliance with the notification protocol and allowing for adequate response time from affected parties.

Consequently, understanding these timeframes helps stakeholders maintain operational integrity and fulfill regulatory requirements.