How long does a Transmission Owner have to notify PJM of a communication capability failure that lasts 30 minutes or longer?

Study for the PJM Transmission Test. Explore topics with flashcards and multiple-choice questions; hints and explanations included for every question. Ace your exam confidently!

A Transmission Owner is required to promptly notify PJM of any communication capability failures that last for 30 minutes or longer. The time frame of 60 minutes is established to ensure timely communication regarding outages or failures that may impact the reliability of the transmission system. This requirement helps PJM coordinate the necessary responses and maintain operational awareness. Addressing issues within this time frame allows for efficient management of resources and ensures that all stakeholders are informed and can take appropriate actions to uphold grid reliability.